High data centre construction costs put Europe at disadvantage in global AI race

High data centre construction costs put Europe at disadvantage in global AI race

02 November 2026 Consultancy.eu
High data centre construction costs put Europe at disadvantage in global AI race

Europe remains the world’s most expensive region in which to build new data centres, according to a benchmark from Turner & Townsend, putting the continent’s ambitions to scale its AI and digital infrastructure under pressure.

To meet surging AI demand, which is driving an unprecedented need for computing power, the world is embarking on a data centre construction race. A key part of the scaling equation is how quickly a country can expand its data centre capacity. From a cost perspective, however, Europe faces competitiveness challenges.

The Global Data Centre Construction Cost Index (DCCI) Turner & Townsend, now in its 10th edition, benchmarks the costs of building new data centres across more than 20 markets. Its central conclusion is that while the Middle East is the most cost-competitive region for new data centres, Europe is the least cost competitive.

“Over the decade since we first published our construction cost index we have seen the data centre industry completely transformed, with capital expenditure on data centres now $800 billion per year, and expected to reach $1.8 trillion by 2050,” said Paul Barry, who leads the research series at Turner & Townsend.

“AI’s exponential demand for computing power, combined with cloud adoption and the growing importance of data and sovereign capacity, is driving data centre investment and development at unprecedented scale, reshaping the construction landscape.”

The benchmark found that half of the 20 most expensive cities in which to build data centres are in Europe, with Zurich, Copenhagen, Oslo, Stockholm and Helsinki all featuring among the ten most expensive locations globally. The top 20 also includes Paris, London, Berlin, Amsterdam and Dublin.

In Zurich, the average cost of data centre construction stands at $15.93 per watt, making it the world’s third most expensive market, behind only Tokyo and Osaka. This is more than 73% higher than in the UAE, where construction costs average $9.20 per watt.

Labour and power

One of the main drivers of rising construction costs is a shortage of skilled professionals. As data centre projects become increasingly complex and larger in scale, they require greater levels of technical expertise and project management experience to deliver. This is having a significant impact on the European market, where just 19% of respondents believe contractor capacity is manageable, compared with 52% globally.

“Europe is seeing strong demand for new, next-generation data centre projects, and many of the most attractive locations, such as Scandinavia, benefit from affordable renewable power and cooler climates, which are well suited to higher-density designs. However, this demand is exceeding contractor capacity and pushing up construction costs in locations such as Copenhagen, Oslo, Stockholm, Helsinki and others,” said Niall O’Reilly, Director at Turner & Townsend.

“In a global race driven by AI, Europe is facing a major skills shortage and risks losing out to international competitors on the technical expertise and leadership experience needed to deliver major data centre projects.”

The survey also found that power availability is a major obstacle to successful project delivery. More than half (52%) of respondents reported that utility connections typically take between one and two years, while almost a third (32%) said the process takes more than two years. This challenge is also playing out across Europe, where grid congestion has already affected data centre projects in countries such as the Netherlands, Belgium, the UK and Sweden.

The most expensive places

The highest-cost locations in the index were Tokyo ($18.28 per watt) and Osaka ($17.15 per watt), followed by Singapore ($15.39 per watt) and Silicon Valley ($15.01 per watt), just behind Europe’s third-most-expensive market, Zurich.

By contrast, the lowest-cost locations in the index were Shanghai ($5.79 per watt), Mumbai ($6.83 per watt), Ho Chi Minh City ($8.32 per watt), Bogotá ($9.13 per watt) and the UAE ($9.20 per watt).